The planned terminal specifications are as follows:
Initial total of 1.2 million barrels of storage capacity with a total of 15 tanks.
Inbound product received via water, Colonial/Laurel pipeline and rail.
All product blending capabilities.
Anticipated products include gasoline, diesel, jet fuel, bio-diesel, ethanol, VGO, blend stocks and additives.
Dock- 700’ LOA, 38 foot draft, no beam restrictions.
Pumping rates of 10,000 barrels per hour
Rail spur capable of receiving and unloading full unit trains of 50-60 cars, two trains per day.
Truck rack- fully automated, open 24 hours, 7 days a week.
Two bays with four arms each, in-line blending capability and pump rates of 550-600 gallons per minute.